by moherlihy » Tue Oct 01, 2024 4:38 pm
Status for: XXX CRESCENT AVE, SAN FRANCISCO CA 94112
Your forecasted fiber live date is: October 2024

My status page says it’s coming this month. Is it really going to happen? When I first placed my order on January 4th, 2022, i was told it would be a few months. Well 33 months later, I’d love to be able to call Comcast and break up with them.

Sonic, please not another rug pull
by loherj » Fri Oct 04, 2024 10:56 am
Thank you for reaching out about your fiber build-out. I was able to locate your account and investigate a little further.

The forecasted go-live is subject to change, and we will do our best to provide accurate estimates. However, it doesn't look like the October estimate will be completed. We hope the build-out for your area will be completed in the next couple of months.

Our fiber build-outs can encounter delays, such as overloaded poles and permitting. These delays can be really impactful, but we try our best to work through them as quickly as we can.

We appreciate your patience while we work to complete this!
Jacob - Community & Escalations Specialist
Sonic