Page 11 of 24
Re: Gigabit Fiber in Bernal Heights
Posted: Fri Nov 10, 2023 11:14 pm
by fiid
I’d appreciate an update too. My status page (south bernal) says November 2023. I’ve been on the waitlist since Dec 2021 and the date keeps pushing out. I don’t believe the dates any more but I’m curious if there is any info at all on when it will be available here or even information on what the next step is.
Re: Gigabit Fiber in Bernal Heights
Posted: Tue Nov 14, 2023 3:12 pm
by dceballos
I'm located off Cortland on Nevada Street. Recently, I've noticed some activity around Precita. According to my construction page, the project is scheduled for completion in November 2023. Typically, if a project is due in a given month and not yet finished, the timeline would be extended by another three months. However, since there's been no such extension so far, I'm optimistic that we're nearing completion.
If anyone spots a Sonic installation truck in the area, please report it here.
Re: Gigabit Fiber in Bernal Heights
Posted: Sat Nov 18, 2023 1:37 pm
by lunulair
dceballos wrote: ↑Tue Nov 14, 2023 3:12 pm
I've noticed some activity around Precita.
What do you mean by 'activity'? (I'm on Crescent and haven't seen a Sonic truck anywhere in the area for
months, after a flurry of splicing at the beginning of the year.)
Re: Gigabit Fiber in Bernal Heights
Posted: Wed Nov 22, 2023 7:26 am
by jcaseysf
Status tool just moved from November to February. Cortland and Banks.
Re: Gigabit Fiber in Bernal Heights
Posted: Thu Nov 23, 2023 10:26 pm
by aatreya
Dane/Sonic - can we get an update/explanation here? I placed my preorder back in
2021. It's now quoting February
2024 in my status tracker. I didn't receive any email about the additional delay, either. This is the
seventh time it has been delayed!
- Is this project actually going to be completed?
- What is the cause of the repeated delays?
Re: Gigabit Fiber in Bernal Heights
Posted: Mon Nov 27, 2023 10:53 pm
by aatreya
Hi Dane/Sonic - any update here?
Re: Gigabit Fiber in Bernal Heights
Posted: Wed Nov 29, 2023 8:03 am
by matt0023
aatreya wrote: ↑Thu Nov 23, 2023 10:26 pm
Dane/Sonic - can we get an update/explanation here? I placed my preorder back in
2021. It's now quoting February
2024 in my status tracker. I didn't receive any email about the additional delay, either. This is the
seventh time it has been delayed!
Yeah same here except I only placed my order in September!

I wonder why they even bothered taking a preorder two years after yours went nowhere. Not a good look.
Re: Gigabit Fiber in Bernal Heights
Posted: Thu Nov 30, 2023 6:17 am
by lunulair
lunulair wrote: ↑Mon Mar 06, 2023 1:55 pm
"Your forecasted fiber live date is: May 2023"
Oh, those were fun times, weren't they?
Re: Gigabit Fiber in Bernal Heights
Posted: Tue Dec 05, 2023 9:44 am
by soonahn
Pushed back again, no updates, no replies, I haven't seen a Sonic truck in my area for the last 3 months.
Re: Gigabit Fiber in Bernal Heights
Posted: Mon Dec 11, 2023 9:30 am
by aatreya
Dane/Sonic, any chance of an update here? Thank you!
aatreya wrote: ↑Thu Nov 23, 2023 10:26 pm
Dane/Sonic - can we get an update/explanation here? I placed my preorder back in
2021. It's now quoting February
2024 in my status tracker. I didn't receive any email about the additional delay, either. This is the
seventh time it has been delayed!
- Is this project actually going to be completed?
- What is the cause of the repeated delays?