Curious about the delay for San Francisco 94134 area

Internet access discussion, including Fusion, IP Broadband, and Gigabit Fiber!
8 posts Page 1 of 1
by izint » Sat Aug 10, 2024 3:12 pm
Just wanted to see if I can get an idea on what caused the recent delay with the 94134 area. Was excited when it moved into construction phase a few months ago, after waiting 2 years of coming soon. Actually saw sonic trucks around doing work on the poles.

The estimated golive date has been slowly pushing out a month or 2 every month, which recently moved to Sept and Oct 2024 (different parts of 94134) for most of July. Then it suddenly jumped to Dec/Jan 2025 last week, then a couple days later its at Apr/June 2025.

Just curious to see what may be causing the big jump in delay.
by jerrielm » Mon Aug 12, 2024 10:00 am
izint wrote: Sat Aug 10, 2024 3:12 pm Just wanted to see if I can get an idea on what caused the recent delay with the 94134 area. Was excited when it moved into construction phase a few months ago, after waiting 2 years of coming soon. Actually saw sonic trucks around doing work on the poles.

The estimated golive date has been slowly pushing out a month or 2 every month, which recently moved to Sept and Oct 2024 (different parts of 94134) for most of July. Then it suddenly jumped to Dec/Jan 2025 last week, then a couple days later its at Apr/June 2025.

Just curious to see what may be causing the big jump in delay.
Hello!

It seems we are waiting for ADA ramp permits before being able to move forward. Hopefully, we are able to get these permits quickly.

Best Wishes!
by coldestfiber » Tue Jan 21, 2025 2:35 pm
It looks like the schedule now is pushed out to Nov :( , probably some additional issues on the permits
by spiritr511 » Sat Feb 15, 2025 11:35 am
ADA ramp permit??? Why? So the people on wheel hair could go online smoother?
by xterminator » Sun Mar 02, 2025 11:50 am
Hello, can we get another status update on this or some more detail? Is progress really halted until this one step is done or has some progress been made in other areas? I'll be honest, hearing that it's being delayed because of a ADA ramp got me bewildered as well.

Thanks!
by wreynolds » Thu Mar 13, 2025 10:36 am
Hi, I am also in this area and have been waiting 2 years for "coming soon" service. Can we please get another status update on this or more detail? My status page says November 2025 and I'm excited to get fiber. Thanks!
by wreynolds » Mon Mar 24, 2025 9:33 pm
Some good news. Today I saw 3 men in utility trucks working on the polls on Felton and Silliman. One of the guys told me they were working on Sonic internet, and I noticed there is a new line labeled Fiber Cable on one pole. They worked on at least 5 blocks today.
by izint » Thu Mar 27, 2025 9:28 pm
wreynolds wrote: Mon Mar 24, 2025 9:33 pm Some good news. Today I saw 3 men in utility trucks working on the polls on Felton and Silliman. One of the guys told me they were working on Sonic internet, and I noticed there is a new line labeled Fiber Cable on one pole. They worked on at least 5 blocks today.
that's some good news, hopefully this November date doesn't push further out