Sorry, I assumed you were in Berkeley. We’re also fully engaged in construction in Oakland, which was also affected by City permitting challenges - both from Oakland, but for the Western portion, a dependency on Berkeley due to the backbone route to the central office being via Berkeley. But the Oakland permit issue was resolved a couple months back and we were able to get it kicked off, and now that Berkeley is also moving again, we won’t end up with stranded network either, that’s key.
This stuff is far harder and more complex than you’d imagine.